Construction on the Crystal City Potomac Yard Transitway will continue through the fall after being delayed by construction conflicts.
“Unforeseen utility conflicts, poor soil conditions and underground obstructions slowed work at several station locations,” the county said on the project’s website.
Arlington County is currently working with contractors to set a new completion date for the project, said county spokesman Eric Balliet, adding that the county will update the community once a schedule has been set.
The county is also holding a public meeting next week to give an update on transitway. The meeting on Oct. 8 will be held at the Residence Inn (2800 S. Potomac Avenue) from 6:30-7:30 p.m.
Currently, the county is working on new transitway lanes and on three of the new stations, Balliet said. Crystal Drive, S. Clark Street and S. Bell Street are affected by the road construction, he added.
“New dedicated transit lanes in Potomac Yard are nearing completion,” Balliet said. “Traffic signs and station signage are being installed, and we’ve started testing LED signs and other technologies that will support the transitway. Our contractor recently resumed construction at several station locations where utility conflicts, poor soils and underground obstructions had slowed work.”
Once completed, the Crystal City Potomac Yard transitway will provide better bus service along the Route 1 corridor, especially during rush hour, the county said.
“The new 4.5-mile Transitway between the Crystal City and Braddock Road Metrorail stations will provide faster, more reliable bus service along the congested Route 1 corridor, with amenities designed to attract new riders,” the county said.
The transitway project broke ground in July 2014 and was originally slated to take 10 months.