The Arlington School Board approved the proposed design for the forthcoming Stratford Middle School in Cherrydale at its meeting Monday night.

The project includes an addition to and renovation of the existing building at 4100 N. Vacation Lane. The building is currently home to the H-B Woodlawn and Stratford programs, which will be moving to the new Wilson School in Rosslyn once both projects are complete.

Specific features of the Stratford project include:

  • 1,000-student middle school
  • 35,000 square foot addition, minimum
  • 144 parking spaces
  • One-way driveway connecting N. Vacation Lane and Old Dominion Drive
  • Traffic and safety improvements on N. Vacation Lane
  • Pedestrian crossing on Old Dominion Drive

The approved addition will be built on the west side of the building and is three stories tall. According to a news release, all renovations will keep the historic existing building in tact, including its south facade.

Architects also provided a second driveway option for the school if VDOT does not approve an exit on Old Dominion Drive.

Funding available for the project ranges from $31.3 million to $36.3 million. The School Board is expected to approve a schematic design in February.

The school system has opposed a push by preservationists to designate Stratford a local historic district, saying it would cause delays and drive up costs. In 1959 Stratford became the first public secondary school in Virginia to be racially integrated.

Stratford Middle School is expected to open in Sept. 2019.

Photos via APS/Quinn Evans Architects