Traffic

Flooding to ‘Significantly’ Delay Reopening of N. Glebe Road

Update at 5 p.m. on Aug. 23 — Glebe Road is now expected to reopen on Monday, Aug. 30.

Earlier: The planned nine-day closure of N. Glebe Road near Chain Bridge is getting longer.

Glebe is currently blocked in both directions between Military Road and Chain Bridge Road for the culmination of a $10 million bridge rehabilitation project. Crews have been working since Friday, Aug. 13 to replace steel beams and the deck of the bridge over Pimmit Run.

But the work zone was damaged today by significant flooding of Pimmit Run and the toppling of two trees and some utility lines. The damage is expected to cause significant delays for the project and the road’s reopening.

From VDOT:

There is a work stoppage on the Glebe Road over Pimmit Run bridge rehabilitation project. Two trees have fallen into the work zone, along with power and cable lines, as well as flooding. This will significantly delay the planned reopening of Glebe Road, originally scheduled for Monday. Once the work zone can be rendered safe and crews can assess the damage, an updated reopening date will be provided.

The department posted video of the flooding on social media, showing raging brown water flowing under the bridge and into the Potomac nearby.

Author

  • Launched in January 2010, ARLnow.com is the place for the latest news, views and things to do around Arlington, Virginia. Started by a Pentagon City resident who has spent the past several years working in local TV news, ARLnow.com seeks to distinguish itself with original, enterprising, up-to-the-minute local coverage.

    View all posts