Deterioration forces additional closures on Arlington-Alexandria bridge

W. Glebe Road Bridge, with a weight limit (Image via Google Maps)

The West Glebe Road Bridge connecting Arlington and Alexandria is dropping down to one lane in each direction after an inspection found deterioration under the bridge’s sidewalk.

According to a press release from Arlington County, one northbound lane and one southbound lane will be open, with one northbound lane being converted into a pedestrian and bicycle path after the closure of the west sidewalk.

“A recent inspection revealed additional deterioration under the west sidewalk and the temporary walking path, which necessitated the sidewalk being closed in this area,” the County said.

Lane closures planned for West Glebe Road Bridge (photo via Arlington County)

In April, the County Board approved a $9.89 million contract — funded jointly by Alexandria and Arlington — for a bridge replacement. The bridge is still in the design process, with construction expected to start next summer. The County said the closures will remain in place until the bridge replacement is completed.

The County noted that this isn’t the first time travel capacity on the bridge has been reduced.

“The routine inspection of the bridge in fall 2018 uncovered deterioration that prompted a vehicle weight restriction of 5 tons and closure of the sidewalks in both directions,” the County said. “The southbound lane across the bridge was converted for the exclusive use of people walking and biking.”