An elevated portion of S. Clark Street is closing today ahead of a planned demolition project.
The $6.3 million project will remove the existing roadway and create new open space, sidewalks, landscaping and lighting, while also creating new development opportunities adjacent to Route 1.
The S. Clark Street overpass was underutilized, according to county traffic studies, but it was useful for those seeking a faster way to get from one side of Crystal City to the other.
Major work on the demolition project is expected to begin in March and wrap up in the summer of 2019. More from Arlington County about what to expect during the project:
The demolition project will generally work from north to south starting with the removal of the 15th Street overpass, scheduled to start in March.
- Throughout the project, some detours will be in place to accommodate removal of the bridge structure. The first of these closures will be on 15th Street in early spring 2018. Details will be shared on the project webpage and in this email update as the temporary street closures are scheduled.
- The at-grade portions of 14th Road South (between 12th and 15th Streets) and South Bell Street (between 15th and 18th Streets) will remain open throughout and after the demolition.
- East-west pedestrian access under elevated Clark Street will be maintained throughout the duration of this project.
- During removal of the bridges over 15th Street and 18th Street, one side of the sidewalk under the bridge will be closed but the other side will remain open.