News

Workers Kick Off Four Months of Ballston Quarter Pedestrian Bridge Construction Tonight

Workers might’ve lifted the new Ballston Quarter pedestrian bridge into place over Wilson Blvd, but it won’t be ready for walkers for months yet.

The county announced yesterday (Thursday) that another four months of work are scheduled on the bridge, which is designed to connect the newly revamped Ballston Quarter development with the neighborhood’s Metro station, linked through the Ballston Exchange development at 4201 Wilson Blvd.

That work means that more road closures are underway on a busy Ballston street.

Tonight (Friday), Wilson Blvd will close between N. Randolph and N. Stuart streets starting at 8 p.m. It won’t reopen until Sunday at 6 p.m.

Then, starting Monday (March 4), county officials say they plan to close the eastbound lanes of Wilson Blvd overnight on weekdays for the next eight weeks. The closure will run from 8 p.m. to 6 a.m. each night, and they’re designed to allow time for “glass installation” on the bridge.

Once that wraps up, workers will close the westbound lanes of Wilson overnight for the next eight weeks to allow for the completion of that work.

Ballston Quarter’s developer, Forest City, also recently secured the County Board’s blessing to continue to use Mosaic Park as a construction staging area through March 22. The developer used the space to assemble the bridge, temporarily delaying planned renovations for the park.

Forest City had hoped to have the bridge ready in time for the development to start opening to customers last fall, but quickly realized it would need more time for the project.

It’s one of many delays for the redevelopment of the old Ballston Common mall — not only has the developer missed its own targets for opening stores to customers, but it’s currently unclear just when its new food court may open for business.

Photo 1 via @ArlingtonDES

Author