Arlington County will begin tearing down the S. Clark Street bridge over 18th Street S. in Crystal City next week, which is expected to generate noise and traffic disruptions for the rest of the month.
Demolition work will begin Monday, June 10, according to the county’s website. The work is part of a $6 million project to tear down the elevated section of S. Clark Street and rebuild a “new open space” in what will soon become a hotspot with the arrival of Amazon’s second headquarters.
“There will be a lot of noise near the work site. No explosives will be used,” the county wrote about the demolition. It added that while debris is being removed, residents “should expect more truck traffic in the area.”
Crews will work Monday through Friday from 8 a.m. to 6 p.m. However, road detours will stay in effect during the weekend and will last for the next two to three weeks. Per Arlington County:
There will be a series of eastbound and westbound closures on 18th Street between South Eads and South Bell Streets during this work. Northbound South Bell Street between 18th and 15th Streets also will be closed. Detours are expected to last for 2-3 weeks, weather permitting.
Drivers will be able to detour around the closure by taking 15th Street S. or using 20th Street S.
The June demolition date for the bridge is slightly after the “tentative” May start date the county originally had hoped for. The project’s demolition of the S. Clark Street overpass over 15th Street S. wrapped up this winter.