News

Amazon Ending Pile Driving Ahead of Schedule at HQ2 Site

As promised last week, Clark Construction is wrapping up pile driving at the Amazon HQ2 site in Pentagon City today, two weeks ahead of schedule.

That’s good news for Amazon’s new neighbors. The noisy work drew protests from those sheltering at home in the apartment buildings around the S. Eads Street construction site, and TV news crews reporting on the complaints.

A spokesman for Clark, the general contractor building the first phase of Amazon’s permanent second headquarters, tells ARLnow that work is proceeding quickly.

“Clark is on track to complete pile driving operations later today, two weeks ahead of our initial projection,” said Marcel Goldstein. “Pile driving is by far the noisiest of all construction operations. Going forward, neighbors should expect to hear the typical noise of dump trucks and other construction equipment/activities occurring on site. We will continue to abide by Arlington County’s noise ordinance.”

The next round of work includes the excavation of nearly a half-million cubic yards of dirt, to make way for the 2.1 million square foot office-and-retail development.

“Crews will continue to advance mass excavation activities on site, which are anticipated to continue for the next 5 months,” the spokesman said. “Mass excavation entails removing 440,000 cubic yards of soil from the jobsite. The team has removed 75,000 cubic yards of soil to date, representing 17% of the total scope of work.”

“Clark remains focused on building a positive relationship and ongoing dialogue with project neighbors,” Goldstein continued. “Community members can contact us and get the latest construction information by visiting our website: metpark678.com.”

The project website says that construction crews are taking measures to stay safe and mitigate the spread of the coronavirus. It also notes that while crews abide by a work schedule set by the county, there’s another noise source that nearby residents may hear at all hours: generators working to drain water from the deepening construction pit.

“The project team is working in compliance with Arlington County’s noise ordinance and operates within the County’s permitted work hours of 7 AM to 9 PM (Mon-Fri) and 9 AM to 9 PM (Sat, Sun, and Holidays),” the website says. “Construction crews continue to utilize generators on site to support dewatering operations, which are running 24 hours a day,” the website says.

Phase 1 of HQ2 is expected to be completed in 2023. A second phase of nearly the same size is planned for the nearby Pen Place site, on the other side of 12th Street S.

Author

  • Launched in January 2010, ARLnow.com is the place for the latest news, views and things to do around Arlington, Virginia. Started by a Pentagon City resident who has spent the past several years working in local TV news, ARLnow.com seeks to distinguish itself with original, enterprising, up-to-the-minute local coverage.

    View all posts