News

Fire Station No. 8 Project Receives Additional Funding

A fire station project in Arlington is getting an additional $2.88 million to add environmental-friendly upgrades and more.

The County Board approved the budget increase Saturday, bringing the total project cost — including contingencies — to $27.92 million. It covers the new Fire Station No. 8 at 4845 Lee Highway, in the Hall’s Hill area, and a temporary facility to allow firefighting operations to continue during construction.

“The new total project budget is $27.92 million which includes: $19.98 million in hard construction costs; $1.21 million for furniture, fixtures and equipment (FF&E); $3.26M in soft costs (design and construction administration fees, County staff time, and permits and inspections); $2.51 million in land acquisitions, and $0.96 million for contingencies,” notes a county staff report.

The fire station will be the first county building to have a “green” (vegetated) roof and solar power, thanks to panels atop the building.

The budget increase approved by the Board covers the solar panels for the 20,522 square-foot facility, placing utilities underground in front of the station along Lee Highway, and other additions, Arlington Dept. of Environmental Services spokesman Peter Golkin said in an email.

The additional cost will be covered by a 2020 bond premium, the county said.

To rein in costs, a value engineering process found savings to the tune of $1.43 million, according to the county. A Public Facilities Review Committee meeting in November detailed those changes, which included reducing the amount of glass used and other adjustments.

Golkin said groundbreaking on the new facility is slated for this fall after the temporary facility is complete.

Photos via Arlington County

Author