(Update at 1:20 p.m.) Construction on the new Long Bridge Park Aquatics, Health and Fitness Facility, originally slated to begin this fall, has been pushed back.
Work on the approximately $80 million facility, located just north of Crystal City near I-395, is now not expected to begin until early 2014, according to Arlington Department of Parks and Recreation spokeswoman Susan Kalish.
“To ensure that we have quality general contractors bidding… we decided to undertake an extensive pre-qualification process,” Kalish explained. “That process is now complete and we have our selected pool of contractors. The bidding process will take place over the next several months. We anticipate that construction will begin in early 2014.”
The authorized bidders on the project are: Manhattan Construction Company, Hess Construction + Engineering Services, The Whiting-Turner Contracting Company, Hensel Phelps Construction Co., Christman/Apex LLC, A Joint Venture Partnership, Balfour Beatty Construction and Gilbane Building Company.
The project’s budget has not changed, Kalish said, but the expected opening date has been pushed back to early 2016. We were earlier told that the opening date had not changed, which is incorrect.
The aquatics center will include a 50 meter by 25 yard fitness and competition pool, a family leisure pool, a hot water therapy pool, a “teaching pool,” and a “free-form water play area that will… have a lazy river, slides, play features and a zero-depth ‘beach’ entry.” The facility will also have amenities like a gym, an exercise center, a climbing wall, an indoor track, racquetball courts and meeting rooms.