Arlington Public Schools is ramping up planning work to build a new school and parking garage at the Arlington Career Center site.
A group tasked with developing the project from 2018-2020 has reconvened and will be working quickly to flesh out the project before the School Board reviews designs this spring.
Planning documents indicate APS envisions building a new, 5-story Career Center along S. Walter Reed Drive that would provide a modern space suited to the 21st-century career and technical skills taught inside.
APS is working on two plans: a “base” plan for a $170.5 million, 260,000-square-foot building for 1,795 students, and an “alternative” plan for a $153 million, 225,000-square-foot building for 1,345 students that is designed to accommodate a future expansion.
Building next to the current ACC building (816 S. Walter Reed Drive) will minimize disruptions and lower costs, according to APS administration.
“One of the things we learned through the last process is that building around an existing high school while the students are in there is cost-prohibitive,” said Lisa Stengle, the APS executive director of planning and evaluation, in a January planning meeting.
ACC houses college and career-readiness programs as well as programs that help recent immigrant students pursue their high school diploma and provide job training for special education students and support for teen parents.
In 2018, APS launched an expansion project to add up to 800 seats to the Career Center, and designs were being finalized in the spring of 2020 when the pandemic hit. The School Board removed the project from its 2021 Capital Improvement Plan (CIP) because it was $84 million, and then $34 million, over budget.
At the time, the board told the school system to focus on smaller renovations to meet rising enrollment. Since then, completed renovations to the Columbia Pike Branch Library created more space for students, and APS is spending around $31 million to add more seats to the current ACC building over the next three years.
But now APS is looking to build once more. The School Board directed Superintendent Francisco Durán in October to add the project to the 2023-32 Capital Improvement Plan, set for approval in June. If approved, the project will go to voters in November as a School Bond referendum.
APS expects to start construction in December 2023 and finish the building in December 2025 and the entire project in 2027.
The graphic below shows how the site will change through the project. (The current ACC building is in light gray, the Columbia Pike library is in dark gray and the above-ground parking garage is in tan.)
Part of the current ACC building (indicated with red dashes) will be demolished to accommodate the above-ground, 400-space parking structure at S. Highland Street and 9th Street S.
The Columbia Pike Branch Library will remain where it is, as will the rest of the ACC building, which APS intends to use as a flexible space. Separately, APS is figuring out what to do with the building long term.