With operating costs projected at twice the original estimates, and construction bids “significantly higher” than anticipated, it may be a case of downsize or die for the proposed Long Bridge Park Aquatics, Health and Fitness Facility.
The project, which was at one point supposed to be under construction by now, is on hold as a result of contractor bids well exceeding the $79.3 million budgeted for the first phase of construction. The county has yet to reveal exactly how high the bids were.
Last night, meanwhile, Arlington County officially acknowledged that a 2012 estimate of the facility’s operating deficit — $1.9 million in Fiscal Year 2020 — has doubled to an annual deficit of $3.8 million. That excludes the cost of running the existing facilities at Long Bridge Park.
After pausing the project, Arlington County Manager Barbara Donnellan instructed her staff to analyze the rising costs of the facility and recommend a course of action. That course of action may be to downsize the county’s lofty ambitions for the “world-class” facility, push it back until economic conditions improve, or scrap it altogether.
Speaking at last night’s Arlington County Democratic Committee meeting, County Board member Mary Hynes left open all possibilities.
“We’re in the process of trying to figure out what the costs will be should the Board decide to move forward on the project at this time,” she said. Speaking to ARLnow.com, Hynes said she would not support spending additional money on the facility at a time when capital funding is urgently needed to increase school capacity.
“We have a certain amount of money set aside for this, we don’t have more than that,” she said. “We have been building pretty significantly for the last 20 years, we’ve spent hundreds and hundreds of millions of dollars in schools. We’ve done fire stations, we’ve done other things. We have a 10 percent self-imposed debt limit and we’ve been bumping around in the 9’s.”
“The only way you get more debt capacity is to raise taxes,” she continued. “I guess that’s a choice that some people would make, that’s not a choice I’d make for a swimming pool.”
Scrapping the facility altogether could prove difficult. Voters have already approved a $42.5 million parks bond for the facility and Vornado has committed $15 million as part of the PenPlace development.
Jay Fisette, a stalwart supporter of the Aquatics, Health and Fitness Facility, says nearly a decade was spent on the center’s design in order to address a community need. Noting that the design of the facility was “incredibly energy efficient,” perhaps driving up costs, Fisette said he’s hoping that those bidding on the project will be swayed to lower their bids and “value engineer” some savings.
“It’s certainly my hope that there’s some ability to look at the bids and talk to the bidders… and narrow that gap,” he said. “The park and the facility design itself came out of a community needs assessment. It was supported by 64 percent of the voters just 14 months ago. I hope we can responsibly move forward.”
Blaming earlier reports that the projected operating costs had increased up to 350 percent on “a complete error” by county staff, Fisette said there are numerous misconceptions about the costs. He added that earlier “exaggerations” about the exact extent of the cost increases have been “celebrated by longtime opponents of the facility.”