New sidewalk along 8th Street S. (file photo)Arlington County staff has agreed to stop trying to jam five-foot-wide sidewalks into residential areas where conditions call for a narrower path.

Deputy County Manager Carol Mitten discussed the change during last week’s Arlington County Board meeting. She said the problem isn’t county policy — which was updated in 2011 — it’s the application of that policy.

The county’s Master Transportation Plan calls for 4-5 foot wide sidewalks in residential neighborhoods, with the narrower sidewalk in areas where it would preserve mature trees, parking, slopes or structures.

Sidewalk width tableCounty staff’s approach, however, has been to design and “start the conversation” with a five-foot-wide sidewalk, even in areas that would otherwise call for the four-foot-wide sidewalk. That led to conflicts and neighborhood consternation.

“There are important accommodations to preserve neighborhood character,” Mitten said. “We think that the policy the Board passed strikes the right balance, whereas our application of the policy perhaps has not.”

While “it is desirable to have a five foot minimum width where possible in order to comply with ADA regulations and for general ease and safe accessibility,” Mitten said, the new approach — of starting the conversation with a four-foot-wide sidewalk where appropriate — “maximizes the opportunity to provide sidewalks along streets where now there are none without compromising the integrity of the overall policy.”

County Board member Jay Fisette said the issue was first raised more than a year ago, after a five-foot-wide sidewalk plan led to the cancellation of some potential Neighborhood Conservation projects.

Libby Garvey, County Board chair, said the county shouldn’t let perfect be the enemy of good, especially in areas where there currently are no sidewalks.

“There are too many streets where to get the perfect sidewalk they’re getting no sidewalk, and that’s not safe for anybody,” she said.

File photo


Snow plow on Jan. 24, 2016The remnants of January’s blizzard may have finally melted, but the storm is still producing policy repercussions in Arlington County.

The county has been soliciting resident feedback on its snow removal effort and there has been no shortage of opinions: some 3,000 constituents responded to an online survey alone.

In response, County Manager Mark Schwartz yesterday presented an initial report for the County Board, outlining a number of snow removal changes that are being considered.

Among the proposed changes:

  • Plow both major roads and residential streets simultaneously during large snow storms, rather than only focusing on major roads and leaving residential streets snow-covered until after the storm.
  • Adding “backup drivers” for large snow storms.
  • Better utilizing staff and contractors “to minimize snow piling at intersections and sidewalks and reduce missed streets.”
  • Improving training and oversight of contractors “to minimize obstructive snow piling.”
  • “Improving technology used to track, monitor and communicate progress during snow and ice removal.”
  • Better utilizing volunteers and coordinating with Arlington’s civic associations.

Longer term changes also being consider include:

  • Adding a snow removal staging area in north Arlington and adding new equipment like backhoe plows and a new snow melter.
  • Odd-even parking requirements, enforcement of snow emergency routes and opening parking garages during large snow  events to reduce obstructions on residential streets for snow plows.

Schwartz is expected to present a more comprehensive report later this year.


2833 N. Harrison Street (photo via Google Map)

Arlington County is spending nearly $900,000 to buy and tear down a house along N. Harrison Street, to expand Chestnut Hills Park.

The County Board voted 5-0 yesterday to approve the purchase of 2833 N. Harrison Street for $820,000. The move comes just a few months after the county purchased an adjacent house for $728,000.

Chestnut Hills Park, near Yorktown High School, recently received a new pre-school playground. The park is said to be one of the most popular and most-used in the county.

Once the house is demolished, the county will expand the park and will “work with the community to enhance its features.” From an Arlington County press release:

For the second time in a year, Arlington County has agreed to buy land to expand the popular Chestnut Hills Park on N. Harrison Street in the Yorktown neighborhood.

The County Board today approved the purchase of a home and surrounding property at 2833 N. Harrison St., adjacent to the park. The agreed purchase price is $820,000 for the 10,405 square foot lot.

“Arlington is serious about looking for opportunities to add to our parkland and open space, and we plan for such purchases. We’re seeing real results for our commitment and planning,” said Arlington County Board Chair Libby Garvey.

The house on the lot the Board agreed to purchase today is a modest rambler, built in 1954, and has no remarkable individual architectural or historical significance. The County plans to deconstruct the house and restore the site as open space. The purchase price was obtained from a licensed Virginia real estate appraiser. The County estimates that closing costs will be about $5,000 and the deconstruction of the house and site restoration will cost about $50,000. The funds will be allocated from Park Land Acquisition funds.

The Board voted 5-0 to approve the acquisition. To read the staff report for this item, visit the County website. Scroll down to Item #21 on the Agenda for the Tuesday, March 15 County Board Meeting.

In the late 1990s, the County asked owners of certain properties along North Harrison Street whether they would be interested in selling their properties to the County to expand Chestnut Hills Park. Between 1996 and 1998, the owners of three properties along North Harrison Street sold their properties to the County. A fourth sold his property in 2015. The park was renovated in 2014. As the park grows, the County will continue to work with the community to enhance its features.

(more…)


Tulip poplar in the Barcroft neighborhood (Flickr pool photo by Dennis Dimick)

Arlington Asks for I-66 Corridor Grants — The Arlington County Board has selected five transportation projects for state potential grant funding. The county is seeking grants from a pool of $5 million allocated by VDOT for initial improvements along the I-66 corridor, ahead of the tolling of the highway. Among the projects Arlington is submitting for consideration: real-time transportation information screens along the Rosslyn-Ballston corridor, expanding certain bus routes, and a series of initiatives including vanpools and a travel planning app for smartphones. [Arlington County]

APS to Renovate Fenwick Center for High School Program — Arlington Public Schools will renovate the 50-year-old Fenwick Center along Columbia Pike for use by the soon-to-be-renamed Arlington Mill High School program. Moving the program will make room at the Arlington Career Center, next door from the Fenwick Center, for the new Arlington Tech initiative. [InsideNova]

Remembering James Kimsey — James Kimsey, the co-founder of AOL, died on March 1 at the age of 76. Kimsey spent his childhood in South Arlington and most recently lived at the very northern tip of Arlington, in a $30 million “castle” known as “The Falls,” which he built around the turn of the century. The house, one of the largest private residences in Virginia and one of the priciest properties in Arlington, was so big that it prompted Arlington County to build a new sewage line. [Falls Church News-Press]

Photo by Dennis Dimick


Dress rehearsal for the St. Peter's Players production of Godspell (Flickr pool photo by Eric)

Vida Fitness Coming to Ballston? — D.C.-based Vida Fitness is reportedly planning a 30,000 square foot gym in Ballston. The plan depends on County Board approval of a site plan amendment for the as-yet-unbuilt final building in the Liberty Center development. Given the high office vacancy rate, local developer Shooshan Co. is proposing to reconfigure what would have been a 20-story office building into a 22-story building that mixes residential, office and retail space. [Washington Business Journal]

‘WeLive’ Close to Opening in Crystal City — WeWork recently opened its new coworking space at 2221 S. Clark Street in Crystal City. Now, the company is nearing an opening for “WeLive,” a communal living space in the same building. WeLive is opening “very soon” and the company is now giving tours to prospective tenants, we hear. A second WeLive location, in Manhattan, recently opened for “beta testing.” [Fast Company]

Rail Was Once Planned for Columbia Pike — In the 1950s planners envisioned Columbia Pike as a rail corridor. That plan was scrapped when Metro was built and the Blue and Yellow lines ran south instead of west. In 2014, of course, a planned streetcar system for the Pike was also nixed. [InsideNova]

County Board Campaign Gets Underway — County Board Chair Libby Garvey and her Democratic primary challenger, Erik Gutshall, both held campaign events on Columbia Pike over the weekend. Garvey said getting out the vote will be the key to victory in the June 14 primary. [InsideNova]

Flickr pool photo by Eric


N. Nash Street is closed to traffic due to pavingUpdated on 3/16/16 — The Trades Center parking garage addition was approved unanimously by the County Board at its Tuesday meeting after a brief discussion.

Earlier: The Arlington County Board approved a trio of two multi-million dollar contracts at its meeting on Saturday.

First, the Board was to consider a $4.85 million contract, with a $0.73 million contingency, to add a third level to the existing two-level parking garage at the Arlington Trades Center near Shirlington.

The Trades Center houses much of Arlington’s maintenance and vehicle fleet operations. According to a staff report, employment at the center has increased to 288 from 174 in 2010. The new garage level would add 155 parking spaces and will follow the increasingly in-vogue “build up, not out” philosophy.

Correction from earlier report: This contract was pulled from the Board’s consent agenda and will be considered at its Tuesday meeting.

Also on Saturday, however, the Board did approve two road paving contracts, together worth nearly $12 million. From a county press release:

“Road maintenance may not be exciting, but it affects everyone in the County,” said Arlington County Board Chair Libby Garvey. “The County is committed to investing in our roads — so that all drivers, walkers and cyclists can travel safely and comfortably.”

The Board voted 5-0 (part of Consent Agenda) to approve the asphalt contracts totaling just under $11.6 million to Finley Asphalt & Sealing and Fort Myer Construction Corporation.

It takes constant effort to maintain Arlington’s 974 lane miles of streets. Each year, the County identifies streets for paving based on pavement conditions, traffic volumes and planned construction by either the County or private developer. Since 2013, the County has averaged the paving of 75 lane miles per year.

Funding for the contracts comes from bonds approved by voters in 2014 and current year Pay-As-You-Go (PAYG), and was included in the Fiscal Year (FY) 2015 – FY 2024 Capital Improvement Plan.


Gray skies over Rosslyn and the Potomac (Flickr pool photo by John Sonderman)

Major Rosslyn Development Approved — A sweeping five-phase redevelopment of 7.65 acres of prime Rosslyn real estate was approved unanimously by the Arlington County Board on Saturday. The Board approved the framework for the development, though final approval will be necessary for each phase. Developers Vornado and Gould Property Company expect to complete the project over the course of 25 years. [Arlington County]

Gun Store Saga Continues — Who owns NOVA Armory, the gun store that’s planning to open in Lyon Park despite community opposition? The man who speaks on behalf of the business and holds its federal firearms sales license isn’t saying, exactly. Dennis Pratte declined further questions after describing it as “a female, minority-owned business” and stating “I may or may not be the owner.” Meanwhile, county leaders say there’s nothing they can legally do to prevent the store from opening. NOVA Armory is planning to a grand opening on March 26. [Washington Post, InsideNova]

Teen Tourist Scammed at Pentagon City Mall — A California teenager on a school trip to Washington was reportedly scammed out of $97 by an armed man at the Pentagon City mall. The man compelled the teen to give him $97 in exchange for what turned out to be a counterfeit $100 bill. [NBC Washington]

Arlington Natives Live Blog Day at Ballston Common Mall — Two friends who grew up in Arlington’s Bluemont neighborhood decided to spend all of Saturday at Ballston Common Mall, ahead of its imminent demise, and live-blog their experience. The blog mixes nostalgia for time spent shopping and working at the mall with observations about the current mix of largely chain restaurants and small, quirky stores. [Things Remembered: A Day at Ballston]

Other County Board Action — On Saturday, the Arlington County Board approved a Memorandum of Understanding to partner with Virginia Tech and join the national MetroLab Network, and voted to accept $731,813 in state funding to support the county’s permanent supportive housing program. [Arlington County, Arlington County]

Flickr pool photo by John Sonderman


The Arlington County Board this weekend is scheduled to consider a massive 7.65 acre redevelopment project that would reshape the Rosslyn skyline.

Developers Vornado and Gould Property Company are proposing a five-phase project that would eventually replace seven existing buildings — the Rosslyn Spectrum Theater, the London Apartments, the Normandy Apartments and four office buildings.

In its place would be 2.5 million square feet of space across five buildings, including 1.8 million square feet of office, 550 residential units, 200 hotel rooms and 45,000 square feet of retail space. Also planned area new, nearly one acre Rosslyn Plaza Park, an Esplanade and two new east-west streets breaking up the super block between N. Kent Street and N. Arlington Ridge Road.

County staff is recommending approval of a Phased Development Site Plan and a rezoning for the project. Each of the five phases will still need its own final site plan approved by the Board.

“The applicant’s proposed redevelopment of the Rosslyn Plaza property will permit the redevelopment of a critical site in
Rosslyn and introduce new elements of public infrastructure identified in the Rosslyn Sector Plan,” wrote county staff, “including the construction of improvements to Wilson Boulevard and N. Kent Street along with two new streets to break up the superblock, creation of the Rosslyn Plaza Park and other public open space improvements, a reconfigured N. Arlington Ridge Road, and bicycle trail improvements including portions of the Esplanade.”

The developers are also proposing a public pedestrian and bicycle bridge over I-66 and the GW Parkway, connecting one of the new roads with the Mt. Vernon Trail.

“The Mount Vernon Trail is used by over 3,000 cyclists on an average day, and provides a trail exit and connection to Rosslyn at Lee Highway near North Lynn Street,” county staff wrote. “The PDSP envisions a pedestrian and bicycle connection to the Mount Vernon Trail, via a bridge at the end of 18th or 19th Street over Interstate 66 and the George Washington Memorial Parkway. Its feasibility has not been determined and will be discussed during future final site plan applications.”

Currently, the apartments in the Rosslyn Plaza site supply fewer than 10 students to Arlington Public Schools. County staff estimate that once completed, the new development will generate a total of 42 APS students — attending Key Elementary School or Arlington Science Focus Elementary School, Williamsburg Middle School and Yorktown High School.

The first phase of the project would demolish the London Apartments, the Spectrum Theater and one of the office buildings. County commissions and the Rosslyn Business Improvement District have been supportive of the project, although some local neighborhood groups have expressed concerns about the height of the proposed buildings and the impact on traffic.

The Board is set to consider the development plan at its meeting on Saturday.


Man pushing a disabled BMW to the Shell station in Shirlington 3/7/16

I-66 Public Hearing at W-L — VDOT is holding a public hearing on the changes planned for I-66 tonight. The hearing is scheduled from 6-8 p.m. at Washington-Lee High School’s cafeteria. Meanwhile, one letter-writer is decrying the “whining” from Arlington residents who complain about the proposed partial widening of I-66 while using it to make a reverse commute to Fairfax County — and the protestations from Arlington policymakers who are more than happy to have large employers come to Ballston and other dense neighborhoods along I-66, thus increasing traffic on the highway. [VDOT, Washington Post]

Wakefield, Yorktown Victorious in Key Games — The Wakefield boys basketball squad defeated Deep Run 50-48 on Saturday to advance to the semifinals of the 5A state basketball tournament. This will be the Warriors’ third semifinal appearance in four seasons. Yorktown’s hockey team, meanwhile, defeated Washington-Lee 5-3 at Kettler Capitals Iceplex Friday night. [InsideNova, Twitter]

Abingdon Elementary Design Approved — On Thursday the Arlington School Board approved a final design for an addition and renovation to Abingdon Elementary School in Fairlington. The project will add 12 classrooms and 136 seats to the school, while renovating the gym, kitchen and media space. [Arlington Public Schools]

Retired Fire Officials Speak Out Against Station Move — Two retired Arlington County Fire Department officials say a proposed relocation of Fire Station 8 from Lee Highway to a county-owned location farther north does not make practical sense and would mostly benefit residents of Fairfax County. Residents around the current fire station and around its proposed new location have been protesting the planned move. [InsideNova]

Arlington Complying With Immigration Detainers —  Arlington County law enforcement is complying with U.S. Immigration and Customs Enforcement detainer requests for jail inmates, but only if ICE reimburses the county for certain expenses and picks up the inmate within 48 hours. Fearing that some jurisdictions are not complying with federal detainers, Republicans in the Virginia General Assembly have proposed bills to make such requests mandatory. [Washington Post]

County Board to Meet With Commission Chairs — The Arlington County Board tonight is holding a meeting with the chairmen of the county’s advisory commissions. ARLnow.com hears that the Board has received complaints about certain commissions overstepping their bounds or operating inefficiently. The meeting will address diversity in commission membership, training for commission members and potential improvements to commission communication and community outreach. [Arlington County]


Construction in front of the Fashion Centre at Pentagon City mall

County Board Work Sessions to Be Broadcast — Arlington TV, the county government’s cable channel, will begin broadcasting County Board work sessions on cable and online this month. First up: the riveting County Board work session on the FY 2017 budget, scheduled for 4 p.m. Thursday. [Arlington County]

Meal Delivery Startup Now Serving Part of Arlington — Galley, a D.C.-based meal delivery startup, says it just expanded its delivery area to include Rosslyn, Courthouse and Clarendon.

ACPD Focusing on Heroin Use and Addiction — The Arlington County Police Department is joining other law enforcement agencies around the region in an initiative to try to curb the distribution, possession and use of heroin. For those battling addiction, there are a number of treatment options in Arlington. [Arlington County]

Schneider to Lead Thrive — Former Democratic County Board candidate Andrew Schneider has been named the new Executive Director of Arlington Thrive, effective today. Thrive is a nonprofit that provides same-day financial assistance to residents in crisis.

Board Thanks Legislators for Hotel Tax Bill — The Arlington County Board is offering its thanks to the state legislators who successfully shepherded Arlington’s hotel tax surcharge reauthorization through the Virginia General Assembly. [Arlington County]


Nelly Custis Park plans (Image via Arlington County)Despite vocal opposition from a few local activists, the Arlington County Board on Tuesday approved the full slate of four proposed Neighborhood Conservation projects.

The County Board allocated $1.4 million for the community improvement projects, which were selected by the citizen-led Neighborhood Conservation Advisory Committee. The committee makes such funding recommendations to the Board twice a year.

Three of the projects were largely uncontroversial — a neighborhood sign for Shirlington, a beautification project for the historic Calloway United Methodist Church cemetery, and street improvements for the 4800 block of 9th Street S. The biggest recommendation, a $800,000 improvement project for Nelly Custis Park (701 24th Street S.), picked up some outspoken critics in the Aurora Highlands neighborhood.

The project would add new plantings, an ADA accessible walkway, improved storm water management and a small play area for school-aged children next to an existing playground. While supporters said most of the community was in favor of the project, a few critics launched a campaign against it, objecting mostly to the playground. Other concerns included the addition of extra pavement from the ADA pathway and “tricycle loop.”

“We heard a number of concerns from the community,” acknowledged Lisa Grandle, of Arlington’s parks and recreation department.

What’s usually an easy vote on the County Board’s “consent agenda” instead became a nearly hour-long discussion that centered around the Neighborhood Conservation process in general and the park project in particular. Board member John Vihstadt led the questioning, and attempted a motion to separate out the Nelly Custis project from the other three, for a vote in March. The motion failed.

The necessity of the conversation seemed to frustrate some Board members. “I‘m disappointed that we’re here tonight, but we’re here,” said Christian Dorsey.

In the end, the Board voted to approve the project as proposed. From a county press release:

The Arlington County Board today approved nearly $1.4 million in funding for four new Neighborhood Conservation projects. The approved projects include street improvements, neighborhood beautification, park improvements, and a neighborhood sign.

The projects, submitted by residents and endorsed by civic associations, are qualified by staff, then evaluated by the Neighborhood Conservation Advisory Committee (NCAC) before coming to the County Board for approval. The NCAC considered 31 projects at its Dec. 10, 2015 meeting and decided to recommend four of them to the County Board for funding.

The Board voted unanimously to approve funding for the four projects. To read the Staff Reporton this Item, visit the County website. Scroll down to Item #10 on the Agenda for the Saturday, Feb. 20, 2016 Regular County Board Agenda.

“We rely on residents to help us identify the best projects to make their neighborhoods safer, stronger and more attractive,” said County Board Chair Libby Garvey. “For more than 50 years, Arlington’s Neighborhood Conservation program has helped build community by funding projects identified by the people who live in the neighborhoods.”

The projects approved by the County Board today are funded by the voter-approved 2014 Neighborhood Conservation Bond. It is the third set of projects to be approved from the $12 million bond. The four approved projects are:

  • $12,500 for Shirlington neighborhood sign – Location and design by the community with staff assistance.  Sign fabrication, sign installation and landscaping.
  • $798,222 for Aurora Highlands Park project – Improvements to Nelly Custis Park including storm water management to correct existing drainage problems; removal of invasive species; improving circulation for accessibility and park use; additional school-age play equipment; new site furnishings; and additional plantings for shade and beautification.
  • $129,625 for Highview Park beautification project – Calloway United Methodist Church Cemetery improvements that include a perimeter fence, interpretive sign, a bench and trash receptacle. A public access easement over the local historic district will allow the public to visit the cemetery and interpret its history.
  • $432,561 for Barcroft street improvement project – 4800 block of 9th Street S to W&OD Trail. Includes completion of missing concrete curb, gutter and sidewalk along the south side of 9th Street S, in the westerly half of the 4800 block, between S Buchanan St and the W&OD Trail. Street milling and paving as needed, including the trail connector between the street dead end and the W&OD Trail. Storm water drainage improvements and the addition of LED Carlyle-style streetlights are a part of the proposed project

The Board also approved the use of $228,000 in additional funds required for street improvements on South Fern Street (project previously approved by the NCAC at the fall 2011 funding session). This additional funding was reviewed and voted on by NCAC at its Jan. 14, 2016 meeting.


View More Stories